Accord to lift gas supply sealed
CHINA has signed an accord with Kazakhstan to expand the capacity of a pipeline network delivering natural gas from central Asia by more than 80 percent.
The two governments agreed to build the Kazakh section of Pipeline "C" that will originate from Turkmenistan and cut through Uzbekistan, China National Petroleum Corp, the country's biggest oil and gas producer, said in its online newsletter yesterday. The link will flank two existing pipelines running through the three central Asian nations.
China is turning to central Asia for gas supplies to diversify fuel sources and to help cut the nation's reliance on coal and oil. Turkmenistan started deliveries in December 2009 and is the only country transporting gas to China by pipeline.
The capacity of Pipeline "C" will rise to 25 billion cubic meters a year by December 2015, boosting the network's capacity to 55 billion cubic meters, CNPC said.
Construction of the 1,305-kilometer Kazakh section will begin early next year and Pipeline "C" will be operational by January 2014 with an initial capacity of 15 billion cubic meters a year, CNPC said.
China and Uzbekistan agreed in April to expand the network's capacity. The central Asian nation, which straddles Turkmenistan and Kazakhstan, signed a pact with CNPC for 10 billion cubic meters of gas a year, the firm said in June last year.
China is also in talks with Russia for gas supply by pipeline.
The two governments agreed to build the Kazakh section of Pipeline "C" that will originate from Turkmenistan and cut through Uzbekistan, China National Petroleum Corp, the country's biggest oil and gas producer, said in its online newsletter yesterday. The link will flank two existing pipelines running through the three central Asian nations.
China is turning to central Asia for gas supplies to diversify fuel sources and to help cut the nation's reliance on coal and oil. Turkmenistan started deliveries in December 2009 and is the only country transporting gas to China by pipeline.
The capacity of Pipeline "C" will rise to 25 billion cubic meters a year by December 2015, boosting the network's capacity to 55 billion cubic meters, CNPC said.
Construction of the 1,305-kilometer Kazakh section will begin early next year and Pipeline "C" will be operational by January 2014 with an initial capacity of 15 billion cubic meters a year, CNPC said.
China and Uzbekistan agreed in April to expand the network's capacity. The central Asian nation, which straddles Turkmenistan and Kazakhstan, signed a pact with CNPC for 10 billion cubic meters of gas a year, the firm said in June last year.
China is also in talks with Russia for gas supply by pipeline.
- About Us
- |
- Terms of Use
- |
-
RSS
- |
- Privacy Policy
- |
- Contact Us
- |
- Shanghai Call Center: 962288
- |
- Tip-off hotline: 52920043
- 娌狪CP璇侊細娌狪CP澶05050403鍙-1
- |
- 浜掕仈缃戞柊闂讳俊鎭湇鍔¤鍙瘉锛31120180004
- |
- 缃戠粶瑙嗗惉璁稿彲璇侊細0909346
- |
- 骞挎挱鐢佃鑺傜洰鍒朵綔璁稿彲璇侊細娌瓧绗354鍙
- |
- 澧炲肩數淇′笟鍔$粡钀ヨ鍙瘉锛氭勃B2-20120012
Copyright 漏 1999- Shanghai Daily. All rights reserved.Preferably viewed with Internet Explorer 8 or newer browsers.