2 new Metro lines
Two new subway lines will be under construction next year and their environmental impact assessment reports are now placed on the official website of Hangzhou Metro Corporation for public review.
The first-phase construction of Metro Line 5 is expected to take 60 months while that of Line 6 will take 56 months. Both are scheduled to begin operating in 2019, according to www.hzmetro.com.
The first phase of Metro Line 5 will run from Century Park Station in Yuhang District to Xiangzhang Road Station in Xiaoshan District. The 48.57-kilometer line will have 17 stations.
Metro Line 6 will start from Shuangpu Station in Xihu District and end at Fengbei Station in Xiaoshan District. The 27km rail link will have 19 stations.
- About Us
- |
- Terms of Use
- |
-
RSS
- |
- Privacy Policy
- |
- Contact Us
- |
- Shanghai Call Center: 962288
- |
- Tip-off hotline: 52920043
- 娌狪CP璇侊細娌狪CP澶05050403鍙-1
- |
- 浜掕仈缃戞柊闂讳俊鎭湇鍔¤鍙瘉锛31120180004
- |
- 缃戠粶瑙嗗惉璁稿彲璇侊細0909346
- |
- 骞挎挱鐢佃鑺傜洰鍒朵綔璁稿彲璇侊細娌瓧绗354鍙
- |
- 澧炲肩數淇′笟鍔$粡钀ヨ鍙瘉锛氭勃B2-20120012
Copyright 漏 1999- Shanghai Daily. All rights reserved.Preferably viewed with Internet Explorer 8 or newer browsers.