The chronology
· On October 18, 2019, steel cutting for the “Adora Magic City” officially started at Waigaoqiao Shipbuilding in Pudong, marking the beginning of the substantive construction phase.
· On November 10, 2020, it fully entered the stage of continuous loading and assembly in the dock, achieving a big leap from detailed design, production design to actual ship loading and assembly.
· On October 18, 2021, the entire ship was connected, and on December 17, 2021, the first floating was achieved within the dock.
· On June 6, 2023, China’s first domestically produced large cruise ship was successfully undocked, demonstrating the strength and strong will of China State Shipbuilding Corp to overcome difficulties and complete this huge system engineering endeavor.
- About Us
- |
- Terms of Use
- |
-
RSS
- |
- Privacy Policy
- |
- Contact Us
- |
- Shanghai Call Center: 962288
- |
- Tip-off hotline: 52920043
- 沪ICP证:沪ICP备05050403号-1
- |
- 互联网新闻信息服务许可证:31120180004
- |
- 网络视听许可证:0909346
- |
- 广播电视节目制作许可证:沪字第354号
- |
- 增值电信业务经营许可证:沪B2-20120012
Copyright © 1999- Shanghai Daily. All rights reserved.Preferably viewed with Internet Explorer 8 or newer browsers.