40 years to decommission nuke plant
JAPAN'S government said yesterday that it will take as many as 40 years to clean up and fully decommission a nuclear plant that went into meltdown after it was struck by a huge tsunami.
Nuclear crisis minister Goshi Hosono acknowledged that decommissioning three wrecked reactors plus spent fuel rods at the Fukushima Dai-ichi plant was an "unprecedented project," and that the process was not "totally foreseeable."
"But we must do it even though we may face difficulties along the way," Hosono said at the release of a lengthy roadmap on the process.
Trade Minister Yukio Edano promised that authorities would move through the process "firmly while ensuring safety at the plant."
He also vowed to pay attention to the concerns of tens of thousands of residents displaced when the plant was knocked out by Japan's March 11 earthquake and tsunami, spawning the world's worst nuclear crisis since the Chernobyl accident in 1986.
Under the plan, approved earlier yesterday following consultation with experts and nuclear regulators, plant operator Tokyo Electric Power Co will start removing spent fuel rods within two years from their pools located on the top floor of each of their reactor buildings.
After that is completed, TEPCO will start removing the melted fuel, most of which is believed to have fallen to the bottom of the core or even down to the bottom of the larger, beaker-shaped containment vessel, a process that is expected to be completed 25 years from now. The location and conditions of the melted fuel is not exactly known.
Completely decommissioning the plant would require five to 10 more years after the fuel debris removal, making the entire process up to 40 years, according to the roadmap.
The process still requires development of robots and technology that can do much of the work remotely because of extremely high radiation levels inside the reactor buildings. Officials are aiming to have such robots by 2013 and start decontaminating the reactor buildings in 2014.
They also have to figure out ways to access each containment vessel and assess the extent of damage, as well as locate holes and cracks through which cooling water is leaking and flooding the area.
The process would place an enormous financial burden on TEPCO. The ministers said the total cost estimate cannot be provided immediately, but promised that there will be no delay for financial reasons.
Prime Minister Yoshihiko Noda announced last Friday that the plant has achieved "cold shutdown conditions," meaning it had been brought to stability.
The announcement paves the way for a new phase that will eventually allow some evacuees back to some areas currently off limits.
Experts say the plant, 230 kilometers northeast of Tokyo, is running with makeshift equipment and is vulnerable to cold and earthquakes.
Nuclear crisis minister Goshi Hosono acknowledged that decommissioning three wrecked reactors plus spent fuel rods at the Fukushima Dai-ichi plant was an "unprecedented project," and that the process was not "totally foreseeable."
"But we must do it even though we may face difficulties along the way," Hosono said at the release of a lengthy roadmap on the process.
Trade Minister Yukio Edano promised that authorities would move through the process "firmly while ensuring safety at the plant."
He also vowed to pay attention to the concerns of tens of thousands of residents displaced when the plant was knocked out by Japan's March 11 earthquake and tsunami, spawning the world's worst nuclear crisis since the Chernobyl accident in 1986.
Under the plan, approved earlier yesterday following consultation with experts and nuclear regulators, plant operator Tokyo Electric Power Co will start removing spent fuel rods within two years from their pools located on the top floor of each of their reactor buildings.
After that is completed, TEPCO will start removing the melted fuel, most of which is believed to have fallen to the bottom of the core or even down to the bottom of the larger, beaker-shaped containment vessel, a process that is expected to be completed 25 years from now. The location and conditions of the melted fuel is not exactly known.
Completely decommissioning the plant would require five to 10 more years after the fuel debris removal, making the entire process up to 40 years, according to the roadmap.
The process still requires development of robots and technology that can do much of the work remotely because of extremely high radiation levels inside the reactor buildings. Officials are aiming to have such robots by 2013 and start decontaminating the reactor buildings in 2014.
They also have to figure out ways to access each containment vessel and assess the extent of damage, as well as locate holes and cracks through which cooling water is leaking and flooding the area.
The process would place an enormous financial burden on TEPCO. The ministers said the total cost estimate cannot be provided immediately, but promised that there will be no delay for financial reasons.
Prime Minister Yoshihiko Noda announced last Friday that the plant has achieved "cold shutdown conditions," meaning it had been brought to stability.
The announcement paves the way for a new phase that will eventually allow some evacuees back to some areas currently off limits.
Experts say the plant, 230 kilometers northeast of Tokyo, is running with makeshift equipment and is vulnerable to cold and earthquakes.
- About Us
- |
- Terms of Use
- |
-
RSS
- |
- Privacy Policy
- |
- Contact Us
- |
- Shanghai Call Center: 962288
- |
- Tip-off hotline: 52920043
- 沪ICP证:沪ICP备05050403号-1
- |
- 互联网新闻信息服务许可证:31120180004
- |
- 网络视听许可证:0909346
- |
- 广播电视节目制作许可证:沪字第354号
- |
- 增值电信业务经营许可证:沪B2-20120012
Copyright © 1999- Shanghai Daily. All rights reserved.Preferably viewed with Internet Explorer 8 or newer browsers.