Speedy progress
ALL the tunnels, bridges and roadbeds for the Hangzhou-Changsha High-Speed Railway within the border of Zhejiang Province have been completed after three years' work.
Workers will start laying the tracks in October and there will be a test run next June, according to the project schedule.
The fast rail is expected to go into service by the end of next year. It will cut the journey from Hangzhou to Changsha, capital of Hunan Province, from 12 to four hours. A trip from Hangzhou to Guangzhou will be shortened from 18 to six hours.
Workers will start laying the tracks in October and there will be a test run next June, according to the project schedule.
The fast rail is expected to go into service by the end of next year. It will cut the journey from Hangzhou to Changsha, capital of Hunan Province, from 12 to four hours. A trip from Hangzhou to Guangzhou will be shortened from 18 to six hours.
- About Us
- |
- Terms of Use
- |
-
RSS
- |
- Privacy Policy
- |
- Contact Us
- |
- Shanghai Call Center: 962288
- |
- Tip-off hotline: 52920043
- 沪ICP证:沪ICP备05050403号-1
- |
- 互联网新闻信息服务许可证:31120180004
- |
- 网络视听许可证:0909346
- |
- 广播电视节目制作许可证:沪字第354号
- |
- 增值电信业务经营许可证:沪B2-20120012
Copyright © 1999- Shanghai Daily. All rights reserved.Preferably viewed with Internet Explorer 8 or newer browsers.