First of 34 wind turbines is put up
THE first wind turbine at the offshore wind power electricity plant near Donghai Bridge was installed over the weekend. The plant will have a total of 34 wind turbines and is expected to be in use before the 2010 World Expo.
The wind turbine is about 90 meters high and weighs 400 tons, with rotating blades about 45 meters long, said a spokesman for the Shanghai Donghai Wind Power Electric Generating Co Ltd.
The Yangshan Port Maritime Authority sent two patrol boats to escort the windmill from the port to the site, a journey that took about six hours, officials said.
The 2.3 billion yuan (US$337 million) plant will generate 260 million kilowatt hours of electricity yearly, a supply for 170,000 families, said the Shanghai Electric Co Ltd.
Construction of the plant began in late 2007.
The wind turbine is about 90 meters high and weighs 400 tons, with rotating blades about 45 meters long, said a spokesman for the Shanghai Donghai Wind Power Electric Generating Co Ltd.
The Yangshan Port Maritime Authority sent two patrol boats to escort the windmill from the port to the site, a journey that took about six hours, officials said.
The 2.3 billion yuan (US$337 million) plant will generate 260 million kilowatt hours of electricity yearly, a supply for 170,000 families, said the Shanghai Electric Co Ltd.
Construction of the plant began in late 2007.
- About Us
- |
- Terms of Use
- |
-
RSS
- |
- Privacy Policy
- |
- Contact Us
- |
- Shanghai Call Center: 962288
- |
- Tip-off hotline: 52920043
- 沪ICP证:沪ICP备05050403号-1
- |
- 互联网新闻信息服务许可证:31120180004
- |
- 网络视听许可证:0909346
- |
- 广播电视节目制作许可证:沪字第354号
- |
- 增值电信业务经营许可证:沪B2-20120012
Copyright © 1999- Shanghai Daily. All rights reserved.Preferably viewed with Internet Explorer 8 or newer browsers.