The shutdown of a pumping station earlier this month that left 350,000 families without running water was blamed yesterday on the carelessness of workers.
Songjiang District was left without water on January 14 when a leak shut down six pumps at the Songjiang No. 2 Water Plant. An investigation by the district government found workers at the factory had failed to patrol the facility on the night of the 13th, which meant they didn't detect the leak in time to stop it from doing major damage.
"The Shanghai Haichao Construction Team, which was in charge of the pump installation in 1995, left a wrench in one of the valves," said Zhang Meng, deputy director of the district. "This meant the valve couldn't close properly."
The director and deputy director of the water plant were sacked, and other officials responsible were also punished.
Songjiang District was left without water on January 14 when a leak shut down six pumps at the Songjiang No. 2 Water Plant. An investigation by the district government found workers at the factory had failed to patrol the facility on the night of the 13th, which meant they didn't detect the leak in time to stop it from doing major damage.
"The Shanghai Haichao Construction Team, which was in charge of the pump installation in 1995, left a wrench in one of the valves," said Zhang Meng, deputy director of the district. "This meant the valve couldn't close properly."
The director and deputy director of the water plant were sacked, and other officials responsible were also punished.
- About Us
- |
- Terms of Use
- |
-
RSS
- |
- Privacy Policy
- |
- Contact Us
- |
- Shanghai Call Center: 962288
- |
- Tip-off hotline: 52920043
- 沪ICP证:沪ICP备05050403号-1
- |
- 互联网新闻信息服务许可证:31120180004
- |
- 网络视听许可证:0909346
- |
- 广播电视节目制作许可证:沪字第354号
- |
- 增值电信业务经营许可证:沪B2-20120012
Copyright © 1999- Shanghai Daily. All rights reserved.Preferably viewed with Internet Explorer 8 or newer browsers.