Related News
BP relief well intercepts ruptured Gulf well
BP Plc yesterday took a significant step toward permanently plugging the ruptured Gulf of Mexico well that caused the world's largest offshore oil spill, the top US official overseeing the spill response said.
Retired Coast Guard Admiral Thad Allen announced late yesterday that BP's relief well bored into the blown-out Macondo well, providing the opening to pump in mud and cement to kill it for good.
"The aggregate data available supports the conclusion that the two wells are joined," Allen said in a statement.
The next step will be to pump cement into the Macondo well near its bottom about 4,000 meters beneath the seabed, Allen said.
He also said tests indicated the reservoir already was sealed off from all parts of the Macondo well after BP pumped in cement from the top on August 5. The so-called "bottom kill" is intended to ensure the job is done.
The final kill will come more than two months after BP sealed off all flow with a cap on the wellhead on July 15. Before then, the well spewed more than 4 million barrels of oil into the sea as BP scrambled to seal it with repeated failed efforts.
The disaster began with a blowout on April 20 that sparked an explosion and fire aboard the Deepwater Horizon drilling rig, killing 11 men.
Once the cement cures, BP will conduct pressure tests to ensure the well is dead, Allen said. He said when drilling resumed on the relief well early Wednesday that the entire process could take four days.
Retired Coast Guard Admiral Thad Allen announced late yesterday that BP's relief well bored into the blown-out Macondo well, providing the opening to pump in mud and cement to kill it for good.
"The aggregate data available supports the conclusion that the two wells are joined," Allen said in a statement.
The next step will be to pump cement into the Macondo well near its bottom about 4,000 meters beneath the seabed, Allen said.
He also said tests indicated the reservoir already was sealed off from all parts of the Macondo well after BP pumped in cement from the top on August 5. The so-called "bottom kill" is intended to ensure the job is done.
The final kill will come more than two months after BP sealed off all flow with a cap on the wellhead on July 15. Before then, the well spewed more than 4 million barrels of oil into the sea as BP scrambled to seal it with repeated failed efforts.
The disaster began with a blowout on April 20 that sparked an explosion and fire aboard the Deepwater Horizon drilling rig, killing 11 men.
Once the cement cures, BP will conduct pressure tests to ensure the well is dead, Allen said. He said when drilling resumed on the relief well early Wednesday that the entire process could take four days.
- About Us
- |
- Terms of Use
- |
-
RSS
- |
- Privacy Policy
- |
- Contact Us
- |
- Shanghai Call Center: 962288
- |
- Tip-off hotline: 52920043
- 沪ICP证:沪ICP备05050403号-1
- |
- 互联网新闻信息服务许可证:31120180004
- |
- 网络视听许可证:0909346
- |
- 广播电视节目制作许可证:沪字第354号
- |
- 增值电信业务经营许可证:沪B2-20120012
Copyright © 1999- Shanghai Daily. All rights reserved.Preferably viewed with Internet Explorer 8 or newer browsers.